In task edit form different rules can be set for calculating planned task start times in MonteCarloProject. Alternative rules are described below.

  • Automatic: task planned start time is set equal to the maximum of predecessors' planned end times. This rule is useful when all predecessors must be finished before task can start and there are no other constraints for the start time. In other words task starts immediately after finishing the predecessor tasks.
  • Flexible: task planned start time cannot be earlier than the maximum of predecessors' planned end times. This rule is useful when all predecessors must be finished before task can start but there can be other constraints for the start time. In other words task can also start at some later time.
  • Manual: task planned start time is set manually. This rule is useful when task does not necessarily have to wait for the predecessors to finish. In other words task can also start earlier.
Cookies user preferences
We use cookies to ensure you to get the best experience on our website. If you decline the use of cookies, this website may not function as expected.
Accept all
Decline all
Read more
Marketing
Set of techniques which have for object the commercial strategy and in particular the market study.
Facebook
Accept
Decline
Google
Accept
Decline
Unknown
Unknown
Accept
Decline
Analytics
Tools used to analyze the data to measure the effectiveness of a website and to understand how it works.
Google Analytics
Accept
Decline
Save