Note that risk management requires MonteCrystal plan.
You can assign risk to a task either in risk or task display.
Assign risk in risk display
Select 'Risks' from the 'Risks' main menu to open the risk list.

Choose the risk by clicking on the risk name.

In risk display choose the task under 'Other tasks' and click on the 'Set risk' button. Scroll down to see all tasks if needed. Risks cannot be assigned to parent tasks.

After the assignment the task moves under the assigned tasks section in the top part of the display. To release the risk click on the 'Release risk' button. Note that risks can be released only from the tasks that belong to one of logged-in user's own projects.

Assign risk in task display
Choose the task in the task table shown in the bottom part of the project display. Scroll the page to see the task table. You can access the task display by clicking on the task name.

Assigned and other risks are shown in the left hand side of the task display. To set the risk click on the 'Set risk' button.

After the assignment the risk moves under the assigned risks section. To release the risk click on the 'Release risk' button.