Following calculation modes are available in MonteCarloProject:
- Automatic:task planned start time is set equal to the maximum of predecessors' planned end times
- Flexible:task planned start time cannot be earlier than the maximum of predecessors' planned end times
- Manual: task planned start time is set manually